PROJECT DESCRIPTION
Under this Rio Tinto contract for work at its Brockman Syncline 1 mine development, NRW will be responsible for the construction of earthworks, roadworks and drainage associated with the primary crusher, overland conveyor and non-process infrastructure, together with construction of haul roads, access roads and concrete structures.
The scope includes drill and blast along with supply and construction of the mechanically stabilised earth ROM wall, two precast concrete overpass tunnels and in-situ concrete foundations for the primary crusher.
The contract is scheduled to commence immediately with a peak workforce of over 300 people and is valued at circa $167 million. The project is in close proximity to other NRW construction sites, including the Brockman 4 to Brockman 2 Haul Road contract and the recently completed Western Turner Northern