NRW was awarded the Gudai-Darri Solar Farm design and construct contract by Rio Tinto, extending civil’s current Gudai-Darri (Kooodaideri) Mine Plant Bulk Earthworks project.
The project is located at the Gudai-Darri mine, 240 kilometres north of Newman in Western Australia,
The scope of work includes:
- Construction of a 34MW solar farm
- Site works July 2021 to February 2022
- Detail earthworks
- 34MVA solar generating
- Tie in to the local 33KV grid
- Tie in to external communication and monitoring systems.
At the projects peak, there will be approximately 120 site-based personnel working on the contract.